Aiken County Public School District

Achieving Excellence

North Augusta High School

  • NAHS Schematic

    In June, we celebrated the completion of Phase One of North Augusta High's new Math & Business Wing, a beautiful 45,610 square foot, two-story facility, with a terrazzo floor entrance, seven business labs downstairs and three groups of paired science classrooms with labs and prep rooms on the second floor.

    Construction is underway now for the next phase, a 124,095 square foot facility full of natural light and classrooms, a Freshman Academy, Media Center, Dining Room and Guidance Area is expected to open for the fall 2017-18 school year.










TIMELINE Phase 2A

  • Design:

    January 2015 – December 2015

    Construction:

    March 2016 – July 2017

    Total Estimated Project Cost:

    $28.9 Million

     

     

     

Architect & Contractor Information

  • Architect: McMillan, Pazdan, Smith

    Contractor: H.G. Reynolds

    Delivery Method: Construction Management At Risk


    Design Phases and Decisions with School Stakeholders’ Involvement

    School Board and Office of School Facilities Approval of Each Phase 

    Continual Building


    Schematic Design







Phase 2B

  • Design:

    January 2015 – December 2015

    Construction:

    July 2017 – November 2018

    Total Estimated Project Cost:

    $24.9 Million